Project Slack

The learner is introduced to flexibility in a project schedule, called project slack.

TBaeten
By
Created Date 09.18.15
Last Updated 09.21.15
Viewed 110 Times
Your browser doesn't support HTML5. System.Collections.Generic.List`1[System.String] System.Collections.Generic.List`1[System.String]
submit to reddit
151

Create multiple-choice games on Wisc-Online and play them on our Chakalaka mobile app!

But that's not all! Explore educational games created by others. Simply search by category or enter agame code number and dive into a world of learning and fun.

Download the Chakalaka mobile app here:
Topics of this game:
  • The difference between the last activity's early finish (EF) time and the project's required completion date is known as:
  • Which term also refers to slack?
  • Total slack is the difference between an activity's early finish (EF) time and late finish (LF) time.
  • Total slack can also be defined as the difference between that activity's early start (ES) time and late start (LS) time.
  • _______ slack indicates the amount of acceleration time needed to complete the project by the required completion time.
  • _______ slack indicates a lack of slack over the entire project.
  • _______ slack indicates the maximum amount of time activities on a path can be delayed without jeopardizing the project's completion by the required completion date.
  • If there's no slack, or if the total slack is zero, the activities on a path don't require acceleration, but also can't be delayed.