PM: Resource Utilization
You'll learn about resource utilization as part of project management.
Created Date
09.18.15
Last Updated
09.21.15
Viewed 30 Times
Create multiple-choice games on Wisc-Online and play them on our Chakalaka mobile app!
But that's not all! Explore educational games created by others. Simply search by category or enter agame code number and dive into a world of learning and fun.
Download the Chakalaka mobile app here:
Topics of this game:
-
A ________ illustrates the expected utilization of resources by time period across a project's time span.
-
The resource requirements plan must indicate the amounts and types of resources needed to perform each activity.
-
_______ develops a schedule that attempts to minimize resource requirement fluctuations.
-
An alternative term for resource leveling is "smoothing."
-
________ applies resources as uniformly as possible without extending the schedule beyond the required completion time.
-
The start of noncritical activities can be delayed beyond their latest start times in order to maintain a uniform level of required resources.
-
Without impacting the project schedule, activities can be delayed only until their positive slack is used up.
-
_______ develops the shortest schedule when the amount of resources is fixed.