PM: Cost Performance

In this learning activity you'll focus on defining Cost Performance and Cost Variance as part of project management.

TBaeten
By
Created Date 09.18.15
Last Updated 09.21.15
Viewed 15 Times
Your browser doesn't support HTML5. System.Collections.Generic.List`1[System.String] System.Collections.Generic.List`1[System.String]
submit to reddit
151

Create multiple-choice games on Wisc-Online and play them on our Chakalaka mobile app!

But that's not all! Explore educational games created by others. Simply search by category or enter agame code number and dive into a world of learning and fun.

Download the Chakalaka mobile app here:
Topics of this game:
  • ____________ measures a project's cost efficiency.
  • Which of these is the correct formula for determining the Cost Performance Index (CPI)?
  • If $75,000 was budgeted, $80,000 was expended, AND $64,000 was the earned value of the work actually performed, what is the correct CPI ratio?
  • A CPI ratio of 0.8 indicates that ________.
  • When the CPI ratio drops below 1.0 or is trending down, corrective action should be taken.
  • ______ is the difference between the cumulative earned value of work performed and the cumulative actual cost.
  • Cost Variance is an indicator of cost performance.
  • Select the proper cost variance formula.